M & A Engineering performed an alignment and line boring exercise on the S Y Adix, a large racing yacht, to correct a misalignment that had prevented the shaft from turning properly.
A survey was undertaken by M&A to determine the extent of the problem and, based on those results, the company was asked to take remedial action at the Pendennis Yard. Pendennis found the work to be cost effective and were pleased to see it completed on schedule - and, as arranged with M&A, at short notice.
New cutlass bearings were installed following the line boring and the components found to work perfectly.